Demolition of existing water basin cooling towers, associated concrete enclosure, site work, and utilities. New Construction of Concrete Cooling Tower Enclosure, Cooling Tower Supports, associated site work, and utilities.
Demolition of existing water basin cooling towers, associated concrete enclosure, site work, and utilities. New Construction of Concrete Cooling Tower Enclosure, Cooling Tower Supports, associated site work, and utilities.
Role: General Contractor
Project Components: Demolition, Metal Studs, Drywall, Flooring, Acoustical Ceiling, Painting, HVAC, Electrical, Fire Alarm, Fire Sprinklers, and a Accordion Folding Partition.
Subcontractors: Bel-Aire Mechanical, Commonwealth Electric, State Tile, Davidson-Bohannon Painting, Apollo Security Group, AZ Verde Fire Protection, and Hufcor.
Main Challenge: Making the best use of the space for the computer tables and the folding partition divider wall.
Solution: Sketch ups, and coordinating the space with the entire project team.
Project Completed: 2018
Role: GC
Project Components: Demolition, Excavation, Specialty Micro Piles, Mechanical, Plumbing, Electrical, Structural, Architectural, Equipment, and Controls.
Subcontractors: Bel-Aire Mechanical, Commonwealth Electric, and Phoenix Cutting Services.
Main Challenge: Soil Conditions and Equipment Lead Time.
Solution: Special Engineering, micro piles, and long lead time procurement.
Project Completed: 2016
Role: Design Build Contractor
Subcontractors: Modular Solutions, Western Underground, G & S Electric, PM Plumbing and Mechanical, and S & S Paving.
Main Challenge: Utility Coordination with the City and the Monte Vista School.
Solution: Brought all parties together to achieve a common goal of keeping the project on track, on budget, and on time through scheduling and push pull activities.
Project completed: 2015
Role: General Contractor
Project Components: Site grading, paving, landscaping, lighting, storm water retention, sidewalk, curb, gutter, colored concrete, crosswalks, and detectable warning systems.
Subcontractors: Ace Asphalt, Swain Electric, and Landscape Professionals
Role: General Contractor
Project Components: Site grading, landscape, hardscape, and a water feature.
Subcontractors: S & S Paving, The Landscape Broker, Casa Companies, Swain Electric
Architect: Greey Pickett.
Main Challenge: Tentative and careful budgeting.
Solution: Flexible scheduling, quality subcontractors.
Role: General Contractor
Project Components: Site grading, paving, landscaping, lighting, storm water retention, sidewalk, colored concrete, crosswalks, curb, gutter, and detectable warning systems
Subcontractors: ACE Asphalt, Swain Electric, Landscape Professionals
Main Challenge: Work directly in front of building in use
Solution: Courtesy, and careful redirection of vehicle and foot traffic
Role: General Contractor
Project Components: Site Grading, concrete paving, Fuel Island, CNG compressor station, sight walls, fencing, lighting, and control modules
Contractors: PM plumbing, and Swain Electric
Main Challenge: Coordination of the entire project with all skilled trades
Solution: Past experience and full coordination and cooperation with the entire project team
Role: Construction Manager at Risk
Project Components: Replace one chiller, replace cooling towers, relocate one chiller to Estrella Mountain Community College, revise and upgrade control systems with re-pipe and re-valve, 48 chilled water supply systems
Subcontractors: Metro Mechanical, Sturgeon Electric, Johnson Controls
Main Challenge: Solution: Quality subcontractors, careful phasing, pre-purchase of major equipment
Role: General Contractor
Project Components: All new central plant and learning facility, metal building, mechanical yard, CMU wall and gate
Subcontractors: Kinetics Mechanical, Commonwealth Electric, GV Masonry, Upright Steel, Johnson Controls, and Desert Painting
Main Challenge: Limited Budget