Arizona Pipe Trades Computer Lab Classroom Buildout

Role: General Contractor

Project Components: Demolition, Metal Studs, Drywall, Flooring, Acoustical Ceiling, Painting, HVAC, Electrical, Fire Alarm, Fire Sprinklers, and a Accordion Folding Partition.

Subcontractors: Bel-Aire Mechanical, Commonwealth Electric, State Tile, Davidson-Bohannon Painting, Apollo Security Group, AZ Verde Fire Protection, and Hufcor.

Main Challenge: Making the best use of the space for the computer tables and the folding partition divider wall.

Solution: Sketch ups, and coordinating the space with the entire project team.

Project Completed: 2018

Posted on

Arizona State Hospital Central Plant Boiler and Controls Replacement

Role: GC

Project Components: Demolition, Excavation, Specialty Micro Piles, Mechanical, Plumbing, Electrical, Structural, Architectural, Equipment, and Controls.

Subcontractors: Bel-Aire Mechanical, Commonwealth Electric, and Phoenix Cutting Services.

Main Challenge: Soil Conditions and Equipment Lead Time.

Solution: Special Engineering, micro piles, and long lead time procurement.

Project Completed: 2016

IMG_3479
IMG_3432

Posted on

SWHD Design Build Turn-Key Modular Building and Site Utilities

Role: Design Build Contractor

Subcontractors: Modular Solutions, Western Underground, G & S Electric, PM Plumbing and Mechanical, and S & S Paving.

Main Challenge: Utility Coordination with the City and the Monte Vista School.

Solution: Brought all parties together to achieve a common goal of keeping the project on track, on budget, and on time through scheduling and push pull activities.

Project completed: 2015

IMG_2409
IMG_2666

Posted on

Chandler Regional Medical Center Morrison Building Parking Lot Addition Project

Role: General Contractor

Project Components: Site grading, paving, landscaping, lighting, storm water retention, sidewalk, colored concrete, crosswalks, curb, gutter, and detectable warning systems

Subcontractors: ACE Asphalt, Swain Electric, Landscape Professionals

Main Challenge: Work directly in front of building in use

Solution: Courtesy, and careful redirection of vehicle and foot traffic

crp3
crp7

Posted on

Sky Harbor Compressed Natural Gas Station

Role: General Contractor

Project Components: Site Grading, concrete paving, Fuel Island, CNG compressor station, sight walls, fencing, lighting, and control modules

Contractors: PM plumbing, and Swain Electric

Main Challenge: Coordination of the entire project with all skilled trades

Solution: Past experience and full coordination and cooperation with the entire project team

OLYMPUS DIGITAL CAMERA
cng4

Posted on

Mesa Community College Central Plant

Role: Construction Manager at Risk

Project Components: Replace one chiller, replace cooling towers, relocate one chiller to Estrella Mountain Community College, revise and upgrade control systems with re-pipe and re-valve, 48 chilled water supply systems

Subcontractors: Metro Mechanical, Sturgeon Electric, Johnson Controls

Main Challenge: Solution: Quality subcontractors, careful phasing, pre-purchase of major equipment

mc7
mc5

Posted on

Pipefitter’s Apprenticeship Bldg. 3: New Central Plant

Role: General Contractor

Project Components: All new central plant and learning facility, metal building, mechanical yard, CMU wall and gate

Subcontractors: Kinetics Mechanical, Commonwealth Electric, GV Masonry, Upright Steel, Johnson Controls, and Desert Painting

Main Challenge: Limited Budget

Solution: Self-performing concrete, drywall, and metal stud work. Along with Structural and Architectural components of the project