Demolition of existing water basin cooling towers, associated concrete enclosure, site work, and utilities. New Construction of Concrete Cooling Tower Enclosure, Cooling Tower Supports, associated site work, and utilities.
Demolition of existing water basin cooling towers, associated concrete enclosure, site work, and utilities. New Construction of Concrete Cooling Tower Enclosure, Cooling Tower Supports, associated site work, and utilities.
Role: General Contractor
Project Components: Demolition, Metal Studs, Drywall, Flooring, Acoustical Ceiling, Painting, HVAC, Electrical, Fire Alarm, Fire Sprinklers, and a Accordion Folding Partition.
Subcontractors: Bel-Aire Mechanical, Commonwealth Electric, State Tile, Davidson-Bohannon Painting, Apollo Security Group, AZ Verde Fire Protection, and Hufcor.
Main Challenge: Making the best use of the space for the computer tables and the folding partition divider wall.
Solution: Sketch ups, and coordinating the space with the entire project team.
Project Completed: 2018
Role: GC
Project Components: Demolition, Excavation, Specialty Micro Piles, Mechanical, Plumbing, Electrical, Structural, Architectural, Equipment, and Controls.
Subcontractors: Bel-Aire Mechanical, Commonwealth Electric, and Phoenix Cutting Services.
Main Challenge: Soil Conditions and Equipment Lead Time.
Solution: Special Engineering, micro piles, and long lead time procurement.
Project Completed: 2016
Role: Design Build Contractor
Subcontractors: Modular Solutions, Western Underground, G & S Electric, PM Plumbing and Mechanical, and S & S Paving.
Main Challenge: Utility Coordination with the City and the Monte Vista School.
Solution: Brought all parties together to achieve a common goal of keeping the project on track, on budget, and on time through scheduling and push pull activities.
Project completed: 2015
Role: Specialty Subcontractor.
Project Components: Structural Concrete Screen Walls, Structural Concrete Equipment Pads, Helical Piers, Structural Steel, Metal Framing, and Standing Seam Metal Roofing.
Main Challenge: Unknown underground utilities and working in the Down Town Phoenix Area.
Solution: Potholing, coordination with the project team, special engineering, and city traffic closure permitting.
Project completed: 2014
Role: General Contractor
Project Components: Site grading, paving, landscaping, lighting, storm water retention, sidewalk, curb, gutter, colored concrete, crosswalks, and detectable warning systems.
Subcontractors: Ace Asphalt, Swain Electric, and Landscape Professionals
Role: Carpentry Subcontractor
Project Components: Exposed exterior wood beams, columns and corbels
Contractor: WE O’Neil
Main Challenge: Coordination with other subcontractors: crowded site, access restrictions, and working at heights
Solution: Safe work planning and work activity pre-planning.
Role: General Contractor
Project Components: Site grading, landscape, hardscape, and a water feature.
Subcontractors: S & S Paving, The Landscape Broker, Casa Companies, Swain Electric
Architect: Greey Pickett.
Main Challenge: Tentative and careful budgeting.
Solution: Flexible scheduling, quality subcontractors.
Role: General Contractor
Project Components: Site grading, paving, landscaping, lighting, storm water retention, sidewalk, colored concrete, crosswalks, curb, gutter, and detectable warning systems
Subcontractors: ACE Asphalt, Swain Electric, Landscape Professionals
Main Challenge: Work directly in front of building in use
Solution: Courtesy, and careful redirection of vehicle and foot traffic
Role: Concrete Subcontractor
Project Components: Complex concrete structures with stairs
Contractors: University Mechanical
Main Challenge: Phasing and coordination
Solution: Full cooperation, and look ahead scheduling