Chandler Gilbert Community College Central Plant

Role: Construction Manager at Risk

Project Components: Add one chiller, replace two existing duplex cooling towers with three new cooling towers, related concrete and steel framing revisions

Subcontractors: Metro Mechanical, Sturgeon Electric, Johnson Controls

Main Challenge: Schedule, budget, and phasing

Solution: Quality subcontractors, and pre-purchase of big ticket items