Role: Construction Manager at Risk
Project Components: Addition of one chiller, replace two duplex cooling towers with three new cooling towers, structural pads and footings, and new structural steel revisions
Subcontractors: Metro Mechanical, Sturgeon Electric, Johnson Controls
Main Challenge: School schedule and related phasing, and a limited budget
Solution: Use of quality subcontractors, and pre-purchasing of cooling towers to establish phasing and lead times