Posted on

Chandler Gilbert Community College Central Plant

Role: Construction Manager at Risk

Project Components: Add one chiller, replace two existing duplex cooling towers with three new cooling towers, related concrete and steel framing revisions

Subcontractors: Metro Mechanical, Sturgeon Electric, Johnson Controls

Main Challenge: Schedule, budget, and phasing

Solution: Quality subcontractors, and pre-purchase of big ticket items

c1
c2
Posted on

Paradise Valley Community College Central Plant

Role: Construction Manager at Risk

Project Components: Addition of one chiller, replace two duplex cooling towers with three new cooling towers, structural pads and footings, and new structural steel revisions

Subcontractors: Metro Mechanical, Sturgeon Electric, Johnson Controls

Main Challenge: School schedule and related phasing, and a limited budget

Solution: Use of quality subcontractors, and pre-purchasing of cooling towers to establish phasing and lead times

OLYMPUS DIGITAL CAMERA
pv4
Posted on

Estrella Mountain Community College Central Plant

Role: Construction Manager at Risk

Project Components: Remove and replace concrete pads and footings, install two new chillers and three new cooling towers, relocate one chiller from PVCC

Subcontractors: IMCOR Mechanical, Sturgeon Electric, Johnson Controls, Upright Steel, Don's Custom Painting

Main Challenge: Schedule, budget, phasing, revising & upgrading controls and energy management systems

Solution: Pre-purchase chillers and cooling towers, and selecting quality subcontractors

em3